Interim Operations at Existing Terminal 1
Existing Terminal 1 remains open and handles current international flights while New Terminal One completes construction and operational readiness testing beside it.
Port Authority of NY & NJBuilt across the south-side sites of JFK’s former Terminals 1, 2, and 3, The New Terminal One is an all-international facility spanning 2.6 million square feet at full completion. Phase 1 (first 14 gates) is Expected Q1 2027; until opening, passengers continue flying from existing JFK Terminal 1.
Expected Q1 2027
Updated from 2026 for systems testing
14 → 23
Full 23-gate completion expected 2030
21
All-international carrier lineup
2.6M sq. ft.
Largest terminal at JFK · Source: PANYNJ
Expected Q1 2027 (adjusted from 2026 for operational readiness and systems testing)
Source: Port Authority / New Terminal OneNew international arrivals and departures halls plus the first 14 gates
Source: Port Authority of NY & NJ2.6 million square feet and 23 gates total (JFK’s largest terminal, replacing former T1, T2, and T3 sites) — Expected 2030
Source: Port Authority of NY & NJOver 300,000 square feet dedicated to dining, retail, and lounges — including flagship airline lounges (e.g., Air France) and Plaza Premium Group lounges (post-security Plaza Premium First & pre-security arrivals lounge)
Source: New Terminal One / PANYNJServed by AirTrain JFK Terminal 1 station and redesigned south-side terminal roadways; until Phase 1 opens, all current T1 carriers continue operating in existing Terminal 1
Source: Port Authority of NY & NJExisting Terminal 1 remains open and handles current international flights while New Terminal One completes construction and operational readiness testing beside it.
Port Authority of NY & NJFirst 14 gates and new international check-in/customs halls open to committed international carriers; exact flight-by-flight transition dates will be published by each airline.
Port Authority / New Terminal OneFinal gates complete after demolition of the existing Terminal 1 structure, bringing total capacity to 23 widebody-capable international gates.
Port Authority of NY & NJSource: Official carrier commitments published by The New Terminal One and the Port Authority of NY & NJ. Exact cutover dates are not yet finalized; verify your departure terminal on your airline itinerary.
Fixed fare booked in advance, driver meets you at arrivals. The price is shown before you pay.
Compare several rental companies at JFK. Deposit and cancellation terms are shown before you pay.
Affiliate links: NYC Now may earn a commission at no extra cost to you.
Phase 1 of JFK’s New Terminal One is expected to open in Q1 2027 (adjusted from earlier 2026 targets to allow additional systems and operational readiness testing). Full completion of all 23 gates is expected in 2030.
According to the Port Authority of NY & NJ, Phase 1 opens with new arrivals and departures halls and the first 14 gates. At full build-out (expected 2030), New Terminal One will span 2.6 million square feet with 23 gates — making it the largest terminal at JFK.
Twenty-one international carriers have committed to New Terminal One, including Air France, KLM, Korean Air, Etihad Airways, Turkish Airlines, LOT Polish Airlines, EVA Air, SAS, Air New Zealand, Philippine Airlines, Qatar Airways, Air Serbia, Neos, Royal Air Maroc, Air China, China Airlines, China Eastern, Gulf Air, Egyptair, Azores Airlines, and Ethiopian Airlines.
The terminal dedicates over 300,000 square feet to dining, retail, and lounges, including flagship airline lounges such as Air France alongside common-use premium spaces operated by Plaza Premium Group (a post-security Plaza Premium First lounge and a pre-security arrivals lounge).